Production Timeline

Singapore PharmaTech is committed to clear and efficient project coordination. The timeline below is indicative only; some stages may overlap, and actual lead times depend on formulation complexity, raw material and packaging availability, testing requirements, artwork approval and order quantity.

  1. 1

    Initial Consultation & Concept Brief

    We review your product objectives, target market, preferred dosage form, ingredients and commercial requirements.

    approximately 2 working days

  2. 2

    Formula Development

    We develop or refine a formula based on your requirements and technical feasibility.

    approximately 5–10 working days

  3. 3

    Feasibility Review & Quotation

    We review the project scope, key materials, packaging and estimated costs before issuing a detailed quotation.

    approximately 3–5 working days

  4. 4

    Sample Development & Evaluation

    A physical sample is prepared for your evaluation. Additional revisions may require extra time.

    approximately 2–4 weeks

  5. 5

    Order Confirmation

    Once the commercial terms, formula and packaging details are confirmed, the project proceeds to procurement and production planning.

    approximately 1–2 working days

  6. 6

    Raw Material & Packaging Procurement

    Required raw materials and packaging components are sourced and scheduled for delivery.

    approximately 4–6 weeks

  7. 7

    Incoming Quality Checks

    Materials are reviewed and checked according to established procedures before use.

    approximately 5–7 working days

  8. 8

    Manufacturing & Packaging

    The product is manufactured and packed according to the approved specifications and production plan.

    approximately 3–4 weeks

  9. 9

    Finished Product Testing & Release

    Finished goods undergo the required quality checks and testing before release.

    approximately 5–10 working days

  10. 10

    Dispatch Preparation

    Released products are prepared and packed for collection or shipment.

    approximately 2 working days

Typical Lead Time

The typical lead time is approximately 2–3 months from order confirmation, subject to the final formula, material availability, packaging, testing and project requirements. If the client supplies approved raw materials, the timeline may be shortened, subject to suitability review and incoming quality checks.